Patna Metro: The construction work of Patna Metro is going on fast. The residents of Patna are eagerly waiting to travel by Metro. The excavation work of Patna MEtro Tunnel is going on in the Moinul Haq Stadium premises. Where two Tunnel Boring Machines (TBM) have been lowered about 16 meters below. This TBM will complete the journey till Patna University. At the same time, the construction of underground metro between Rukanpura and Patna Junction can start from July.

Tunnel digging work in progress

The construction work of underground metro is to start between Patna Junction and Rukanpura. According to media reports, its construction work is likely to start in July. Soon the agency will be selected through tender and soil testing will be done. After this, the work of making tunnel with Tunnel Boring Machine (TBM) will be started here too. Let us tell you that tunnel excavation work is going on in the Moinul Haq Stadium premises.

Patna Metro has two corridors, underground travel will be more

Patna Metro will be built in two corridors. At present, the construction work of elevated metro is going on between Saguna Mod to Patalipatra Railway Station and Mithapur to Khemnichak in Corridor One. Whereas in Corridor Two, work is going on between Rajendra Nagar Terminal and Malahi Pakdi. In Patna Metro, more part of elevated than elevated will remain underground. The metro will be 32.497 km long, whose construction work is targeted to be completed in 2026.

New shortcut route fixed for Patna-Ranchi Vande Bharat train, know what will be different from the journey of Janshatabdi?

traveling underground

Corridor 1: Its part is 17.9333 km. In which there will be 10.54 km underground metro. That is, you will be able to travel this distance underground by metro. While 7.393 km will be built above the ground i.e. elevated metro.

Elevated station will remain here..

In Corridor 1, Danapur, Saguna Mode, RPS Mod, Patliputra, Mithapur, Ramakrishnanagar, Jaganpura and Khemnichak stations will remain elevated. While Corridor 2 will have Patliputra Bus Terminal, Zeromile, Bhootnath, Khemnichak and Malahi Pakdi elevated stations.

Underground stations will remain here..

While talking about underground stations, Patna Junction, Vidyut Bhawan, Vikas Bhawan, Chidiyaghar, Rajabazar, Rukanpura will have underground metro stations in Corridor 1. Patna Junction, Akashvani, Gandhi Maidan, PMCH, Patna University, Moinul Haq Stadium in Corridor 2. And there will be underground stations in Rajendranagar. Let us inform that the meeting point of both the corridors will be near Khemnichak and Patna Junction. This will be called interchange station.